Building Project Update
by Kim Buryanek
November 07, 2011
The building renovation project will soon be making steady progress.
The bus barn building materials arrived the first of November. The building will be erected after the concrete is poured and ready for the building to be assembled.
The precast walls for the main building are expected to arrive the week of November 7 and the week of November 14. Many of the subcontractors are not able to move forward with their work on the project until after the precast walls have been installed.
According to the general contractors that were awarded the bids, the bus barn and the main building are still on schedule to be completed in February and August, respectively.